Product data

Customer
CGN SA Lausanne

Year of completion
2016

MS Italie

CGN splittet the renovation into different subprojects. To our pleasure Shiptec was awarded with the task for the shipbuilding- and steel constructions on the hull as well as on the upper decks.

The works were executed on the dry dock of CGN in Lausanne. The most intensive work phase was from September to November 2015. Smaller works dragged on to February – March 2016.

 

 TECHNICAL DATA:

Length over all:61.50 m
Width over all:14.00 m
Displacement:300 t
Person:560 people